During a Sprint, when is new work or further decomposition o...

During a Sprint, when is new work or further decomposition of work added to the Sprint? (choose the best answer) A. During the Daily Scrum B. When the Scrum Master has time to enter it. C. When the Product Owner identifies new work. D. As soon as possible after it is identified.

During a Sprint, when is new work or further decomposition of work added to the Sprint? (choose the best answer)
A. During the Daily Scrum
B. When the Scrum Master has time to enter it.
C. When the Product Owner identifies new work.
D. As soon as possible after it is identified.