What happens when a Sprint is cancelled? (Choose the best two answers)
- All incomplete Product Backlog items return to the Product Backlog.
- The Sprint Backlog items are discarded and new Product Backlog items are put in place.
- At the Sprint Retrospective the Product Owner determines who was responsible for that.
- Any completed and "Done" Product Backlog items are reviewed.