Engenharia de Produção ·

Pesquisa Operacional 2

Send your question to AI and receive an answer instantly

Ask Question

Preview text

04 11 22 Folga DTT e DTI DTI DTT t DTT H DCTH 44 DTIH 44 5 39 DTT G DTIH 39 DTIG 39 7 32 DTTE DTT F DTIG 32 DTIE 32 6 26 DTIF 32 4 28 DTT D DTIF 28 DTID 28 5 23 DTT C DTIE 26 DTIC 26 6 20 menor DTTB DTIC 20 DTIB 20 12 8 DTIA DTIB 8 DTIA 8 8 0 atividade DCI DCT DTT DTI A 0 8 8 0 B 8 20 20 8 C 20 26 26 20 D 20 25 28 23 E 26 32 32 26 F 25 29 32 28 G 32 39 39 32 H 39 44 44 39 DTT DCT 0 Folga 0 DTI DCI 0 Caminho crítico A B C E G H duração 44